Design, construction and financing of the GO! extension Hazenakker primary school

Details

Client
Seminpark voor GO! Onderwijs
Architect
ABDM Bvba - Architectuurbureau Dirk Martens - Zingem
Execution period
aug 2015 - jan 2017
Execution cost
2.595.658
Site
Gentbrugge

About the project

Wyckaert was awarded the construction project following a competitive call for tenders issued by GO!. The project comprises the design, construction and financing of a sports hall and classrooms. The plan of approach with special attention to safety measures was of great importance during the construction work in the school environment that continued to be operational.
The works include structural work, finishing, technical facilities and landscaping.

 

Key information

Construction surface2.000 m²
No. floors2
Surface surrounding area1.400 m²